Background Image
Previous Page  8-9 / 52 Next Page
Information
Show Menu
Previous Page 8-9 / 52 Next Page
Page Background

Fabric belting is usually installed so that most of the take-up

travel is available for subsequent increase in belt length.

The belt may be tensioned with a suitable take-up

device as follows:

1.

When the counterweight is on: Tie the take-up off 6 in.

to 8 in. (150mm to 200mm) above the desired running

position. (Consideration may have to be made for

excessive sag.) Next, pull the belt until the take-up starts

to lift and the tie-off ropes become slack. Make the final

splice allowing a minimum of belt slack.

2.

When the counterweight is not on: Splicing without the

counterweight installed is undesirable, however the

following procedure should be employed if necessary.

Use suitable belt clamps to hold the take-up pulley 6” to 8”

(150mm to 200mm) above the desired running position.

(Consideration may have to be made for excessive sag.)

Pull the belt to its running tension, which can only be

estimated in this situation. Judgment in estimating this

tension will improve with the experience of the splicer.

Take-Up Travel and Initial Position

Tables 2-1 and 2-2 show the recommended minimum take-up

travel and initial take-up position, respectively.

This table is a general guideline. See individual product

brochure for more specific data.

Take-up location position per Table 2-2.

Drive location at or near the high-tension end of the conveyor.

Only short feeder belts and similar would normally be

vulcanized on conveyors with a manual take-up.

+ Take up conditions and travel amounts shown in Table 2-1.

Table 2-2 Recommended Initial Take-Up Position +

Carcass Material (Warp)

Percent Available For

Length Increase

Percent Available For

Length Decrease

Steel

25%

20%

Nylon, Polyester, Aramid, Fiberglass

90%

10%

If calculating in S.I. units, multiply the belt weight (kg/m)

times the vertical lift and add 10%. For example, assume

a 60-kg/m belt and a 100 m high slope. The approximate

pull is (60 x 100) x 1.1 = 6600kg.

If the conveying side and the return side have been fed on

separately, the final splice can be made at the bottom of the

slope where the ends of the belt meet. In some situations, it is

advisable to use a suitable temporary splice to index the belt

and complete the final splice at the original location. Making the

final splice at the top of the slope is possible but a greater force

will be required to remove the sag and lift the counterweight.

Belt clamps must be used on the final pull. The system

illustrated in Fig. 2-6 will avoid dismantling the work area by

allowing a suitable length of belt to lie back over the clamp.

Tensioning the Belt

Once the belt has been pulled onto the conveyor system,

it must be tensioned before splicing to facilitate correct

positioning of the take-up and to eliminate sag. The tensioning

operation takes place at the location where the last splice will

be made. After final tensioning, clamps are placed on each

end of the belt. These are made of steel and have a clamping

surface as indicated in Fig. 2-6.

Tension is applied by means of a power device which is used to

pretension the belt before “clamping off.”

When tension measuring load cells or scales are used, they

are rigged to measure the pull on the take-up pulley. The belt

is pulled until the load cell or scales register a tension equal to

or slightly greater than the recommended take-up force. Make

allowance for an amount of belt necessary to correctly position

the counterweight from this point.

Certain basic statements and recommendations can be made

about tensioning for splicing:

1.

Belts, which are tensioned by pulling in only one direction,

require more splicing tension than those pulled in both

directions.

2.

Belts spliced at the top of the slope require more tension

while splicing than those spliced at the bottom.

3.

Slope belts having an anti-rollback device, which cannot be

released, must be tensioned by pulling in the direction of

belt travel only.

4.

Check the belt frequently during tensioning to ensure that

the belt is free and not binding at any place.

5.

During the final tensioning pull, be sure the ends of the belt

are lined up properly.

Conveyor installations having limited take-up travel should be

spliced to a tension based on the loaded running tension. This

tension should be specified by Continental ContiTech. and

measured by suitable load cells or dynamometers. Where it

is practical, fabric belts should be run for several weeks with

mechanical fasteners before making the final vulcanized splice.

Obtaining the required tension depends heavily on the

experience of the individual making the splice. It is possible for

a gravity-type take-up to damage the conveyor structure if it is

positioned too close to the forward or upward stop. Too much

tension applied to a relatively short belt may thus have a harmful

effect on the pulley shafts and bearings as well as the belt.

Grade 8 Bolts – 1 in. to 1¼ in. – Hard Nuts and Washers

Weld 1/2" x 2" Flat Bar to Tube to Bow Slightly

Square Tubing – min. 1/4 in. wall – A-53

Adequate plate,

eye and shackle

for load

Detail of Square Tube

End Typical grind the

weld on the round tube

flush with the square tube

Internal Sleeve

so tube doesn’t

crush

Weld Keystock

position to

prevent bolt

turning

Fig. 2-6: Tension Clamp for Splicing

8

7

Conveyor Belt

Fabric Splice Manual

Table 2-1 Recommended Minimum Take-Up Travel In Percent Of Center Distance

Type Of Take-Up And Carcass Material (Warp)

Percent Of Rated Tension

100%

75%

50%

Manual Take-Up

Nylon

4.0%

3.0%

2.0%

Polyester

2.5%

2.0%

1.5%

Aramid

2.0%

1.5%

1.0%

Fiberglass

1.0%

0.75%

0.5%

Automatic Take-Up

Nylon

3.0%

2.50%

1.50%

Polyester

1.7%

1.25%

0.75%

Aramid

1.5%

1.0%

0.75%

Fiberglass

0.5%

0.4%

0.25%

Steel

0.3%

0.23%

0.15%

Conveyor Belt

Fabric Splice Manual